Iron County Courthouse Restoration/Renovation Project
|
|||||||||||||||||||||||||||||||||||||||||
CONTRACTORS/SUBCONTRACTORS Project Contractor: Miron Construction Company, Ron Schmidt, Superintendent Architect: STS Consultants, Ltd. Project Subcontractors: Curt Erickson Plaster Clock Mechanism and Hand Restoration: Mickey Diqui, Max Woelffer, and Bill Jacobson
|
Floor Leveling in Old Board Meeting Room by Miron Construction (Gary Johnson and Rick Anderson)
Technology and Communication Cabling by Cabl |
Work Continues on New Doorway from Annex Addition by Rick anderson of Miron Construction |
Electrical Work Continues in the Courthouse by Dave Oleksy of MJ Electric |
Mechanical and Drywall Work by Brian Johnson of Rick's Mechanical and Mike Mitchell of Eland Drywall |
Drywall Finishing Touches by Jamie Erickson of Eland Drywall |
|
Ceiling Board Preparation by Omni Painting and Installation of Miron Construction Ron Schmidt and Rick Andersen
|
|
Bill Meeuwsen of Omni - Applying Stain and Varnish to Beams and New Ceiling in New County Board Meeting Room
|
|
Ceiling Tile Repair by Miron Construction-Rick Anderson. Omni Painting Crew Bill Meeuwsen and Bill Quinlan (Ceiling: Natural Tan Beams: Red bud) The Painting Begins in the Circuit Courtroom! |
|
Jewel of Heaven (Green) and Bagel (Tan) Being Used on Walls and Decorative Pieces. (Note: The Courtroom Focal Point is Natural - the Colors Being Enhanced Only by Cleaning by Omni Painting) |
|
Plaster Repair and New Corners in Courtroom by Curt Erickson Plaster Crew |
Kevin Sundholm From Miron Construction Working on New Entrance to Bell Tower |
Lyle Perry with Rick's Mechanical installing pipe in Annex Addition |
|
Arch Rebuilding by Miron Construction Left: Jim Carlson Right: Dave Bauman |
|
Bell is ready for Return to Tower Left: Ron Schmidt ~ Right: Rick Anderson |
Crane Operator ~ Ed Plym |
Bell Being Delivered to Tower |
|
Bell Placed on Tower Base |
|
Drywall Finishing Work in the Circuit Courtroom by Randy Sheffer of Curt Erickson Plaster |
|
The Mitchell Brothers from Eland Drywall Working in the Main Hallway Left: Mark ~ Right: Mike |
|
Ron Schmidt, Miron superintendent, Checking the Progress on the New Bell Tower Entrance. Note New Railing at Observation Deck |
Arch Replacement Begins by Miron Construction Left: Jim Carlson ~ Right: Dave Bauman |
Annex New Window Installation by St. George Glass Outside: Brad Straloe ~ Inside: Rick Ekstrom |
|
Taping and Plaster Work by Jamie Erickson of Eland Drywall |
|
Scaffolding Set-up for Pending Annex Addition Brick Work |
|
We invite you to review our web page as the Iron County Courthouse Restoration/Renovation Project progresses. This is an exciting time for Iron County as we restore its "Jewel" and we want to share it with you. Back to Governmental Offices IndexThank you to Sue Passamani for providing the content and photos for this and many pages of the www.iron.org website and renovation pages. |
|